Eighty-four FTTP installations have been completed in Park Glen, with just 10 left to go — and four of those are scheduled to be done soon! In the next few weeks, the next fiber route (south of Ross Street, from 4th Street to Gorin Street) will be spliced and ready for installations, which will complete Zone 1. SKT Internet customers in Zone 2 will be enjoying their new fiber connections within the next 60 to 90 days. Looking ahead, Zone 3 should be completed by the spring of 2018.